Precautions for starting, running, and stopping Weifang generator sets!

Time:2024-08-13 15:19:03  Edit:HuaQuan

The Weifang generator set is started to enable the unit to operate and stop when the work is completed. So, what is the specific process of this series? What are the things to pay attention to in order for the Weifang generator set to complete the power supply work normally? Huaquan Power provides detailed information.

Manual testing machine
1. Weifang generator set manual start: After testing the alarm system to be normal, switch the control switch to the manual (MAN) position, and the generator can start on its own.
2. Generator shutdown: Turn the control switch to the STOP position or press the red emergency stop button to stop the generator operation. In case of emergency, pressing the emergency stop button directly can force the machine to stop. If the red emergency stop button is pressed, it must return to its original position, otherwise the generator will not start.

 Several points to note during the operation of Weifang generator sets:
1. AC ammeter: Check if the needle indication is normal, switch the current switch, measure the phase current values between each phase sequence, and ensure that the difference between each phase sequence does not exceed 10%.
2. AC voltmeter: Check if the voltage indicated by the pointer is normal.
3. Is the oil pressure indicated by the oil pressure gauge within the normal range.
4. Charging meter: whether the pointer is in the (+) direction.
5. Is the water temperature indicated by the water temperature gauge within the normal range of 65 ℃ to 93 ℃.
6. Tachometer: Whether the engine's RPM is appropriate. (60Hz is 1800 rpm)
7. Is there any abnormal sound or vibration in the Weichai diesel generator engine used in real estate.

Automatic switching control
1. Switch the control switch to AUTO and use it in conjunction with the power automatic transfer switch (ATS). The control switch must also be placed in the automatic position. When the mains power stops, A · T · S will send a start signal to the generator control system, and the Weichai diesel generator used in real estate will automatically start.
2. When the control switch is switched to STOP or remains in automatic mode, but the mains power has been restored, ATS will send a stop signal and the generator will automatically stop.

Attention: In case of automatic shutdown of a running generator due to faults such as overspeed, high water temperature, low oil pressure, etc., the fault reset button must be pressed down after troubleshooting to prepare for restart.

Huaquan Power introduces that only by doing the above things well can the generator set operate and shut down normally and smoothly. Have you achieved these things when using Weifang generator set? I hope the above introduction can provide users with reference.

Sales hotline: +86 15905360672
WeChat customer service: +86 15905360672
Email address: huaquan@huaquanpower.com
Official website: https://www.huaquanpower.com
Production Base: No. 11666 Guting Street, Economic Development Zone, Weifang City, Shandong Province
Company Name:SHANDONG HUAQUAN POWER CO.,LTD